PROJECT
SUMMARY
From the surface, the Bridge Street Bridge Project in Southfield,
Michigan does not appear to be much different than any other bridge
installation. As the sole means of access to the Bridge Street Industrial
Subdivision, the project consists of two parallel bridges with one
serving incoming traffic and the other, outgoing. Each is constructed
of reinforced concrete with similar traffic barrier and sidewalk configurations.
This similarity of appearance belies the radical difference in the
actual structures with regard to their reinforcement systems and materials.
Structure A, which services traffic entering the subdivision, was
constructed of standard AASHTO precast concrete beams, reinforced
with conventional steel elements. Structure B, carrying outgoing traffic,
was constructed of precast concrete double-tee beams reinforced not
with steel, but with elements manufactured of carbon fiber reinforced
polymer (CFPR). The use of CFRP offers several distinct advantages
over reinforcing steel in concrete construction, on of which is the
virtual elimination of deterioration due to corrosion, a common problem
among conventionally reinforced bridges.
The quantity and extent to which CFRP was used in place of steel in
Structure B has set a new precedent in advanced composite technology
in a civil engineering application. To assure the success of a project
with no precursor, special programs for the production, testing, erection,
instrumentation, and monitoring of these CFRP-reinforced beams were
implemented. The design, management, and construction of this $8.5
million structural system project form the basis of our ACEC 2003
Engineering Excellence Awards joint entry.
The Bridge Street Bridge Project made extensive use of a cutting edge
material with the input and support of a team consisting of members
from around the world. For example, quality CFRP materials were purchased
from manufacturers in Japan and Canada. Funding was provided by the
Federal Highway Administration through the cooperation of the Michigan
Department of Transportation. In addition, four (4) separate contracts
were established: one for the fabrication of the precast beams, one
for the Test Beam program, and separate agreements for the site construction
and structural instrumentation and monitoring. Joining the City of
Southfield, HRC, and LTU as part of the Project Team were:
· The Federal Highway Administration (FHWA) - Funding Procurement
· The Michigan Department of Transportation (MDOT) - Design
Guidance & Support
· Tokyo Rope Mfg., Ltd., Mitsubishi Chemical Corp. & Autocon
Composites, Inc. - CFRP Material Manufacturers
· Angelo Iafrate Construction Co. - General Contractor
· Hollowcore, Inc./Prestressed Systems, Inc. - Precast Contractor
· Construction Technology Laboratories - Testing, Instrumentation
& Monitoring Contractor
The
innovative design approach for Structure B, which was based on research
conducted by LTU and the University of Windsor, Ontario, called for
the use of CFRP in nearly all aspects of the structural reinforcement.
Inside each double-tee beam are sixty (60) strands of pretensioned
CFRP cable as well as a variety of non-prestressed CFRP reinforcement
manufactured in bent shapes and straight rods. Steel reinforcing bars
used for shear reinforcement, and all miscellaneous embedded materials
used in Structure B, were made of stainless steel.
Standard techniques for prestressing of conventional steel strands
could not be used during the CFRP prestressing operations. A simplified
method for the prestressing of the CFRP tendons was first developed
in Japan using conventional steel strands and steel transition couplers.
Due to severe geometric constraints associated with the placement
of thirty (30) tendons in each stem and beam production economies,
a new and innovative prestressing method had to be developed. This
new method utilized rotational restraining transition couplers, both
conventional steel strand and CFRP strand, and separate anchor devices
for each of the sixty (60) tendons that were prestressed in each beam.
Structure B features a unique method of external post-tensioning using
a series of four (4) - 1½ in. (40mm) diameter cables made of
CFRP on the underside of each double-tee beam. An innovative bearing
support technique called a tendon alignment bearing shoe was designed
for these cables. Various engineering constraints and constructability
issues were successfully resolved through this original design.
FUTURE
VALUE TO THE ENGINEERING PROFESSION
The Bridge Street Bridge Project has met the immediate need to provide
continuous access to the Bridge Street Industrial Park. At the same
time, the dual bridge concept has provided an opportunity for an on-going
study and comparison between the conventional steel and innovative
CFRP-reinforced structural systems. A complex system of instrumentation
and monitoring devices was embedded and exterior-mounted to the structural
elements of both bridges during construction. Through this instrumentation,
the behavior of the structural system will be continuously monitored
over the next five (5) years. The data collected will be made available
to researchers, federal and state transportation authorities, and
the National Science Foundation. It is hoped that the successful construction
of this innovative structural system and the study of its behavior,
will result in future investigation and usage of advanced CFRP composites
in many more applications in and beyond civil engineering.
It
is anticipated that an increased life span and significantly reduced
maintenance costs over that of a conventionally reinforced bridge
will be the primary benefits of choosing to reinforce Structure B
with CFRP. When maintenance or repair does become necessary in the
future, the dual bridge concept will allow the City to completely
close one bridge down for service while traffic is temporarily redirected
to the second bridge. This will provide uninterrupted access to the
Bridge Street Industrial Subdivision as was done during construction.
<
return to index >
Tokyo
Rope Company Representatives and Mayor Brenda L. Lawrence (City of Southfield)


Organizations
from US, Canada and Japan were involved in the project

Mrs
Brenda L. Lawrence,
Mayor of the City of Southfield

Guests
attended Opening Ceremony

Dr.
Chambers and Mr. Donald Fracassi, former Mayor of Southfield

Members of the City of Southfield Council

City
Council and Mayor Brenda Lawrence

Representatives
from Mitsubishi Chemical Company and Sumitomo, Japan

Mr.
Don Gross, City Administrator

Mr.
Tanaka, President of Tokyo Rope Company

Mr.
George Hubbell, VP of HRC Consulting Engineer, Inc.
and members the City of Southfield Council

Members
of the City Council

Lawrence
Technological Universities Administration
<
return to index >